Where Breach of Contract and Tortious Interference Collide

Originally posted 2022-01-03 09:00:05.

Claims for breach of contract are numerous in the construction law world.  Without these claims we construction attorneys would have a hard time keeping the doors open. A 2021 case examined a different sort of claim that could arise (though, “spoiler alert” did not in this case) during the course of a construction project.  That type of claim is one for tortious interference with business expectancy.

In Clark Nexsen, Inc. et. al v. Rebkee, the U. S. District Court for the Eastern District of Virginia gave a great explanation of the law of this type of claim in analyzing the following basic facts:

In 2018, Clark Nexsen, Inc. (“Clark”) and MEB General Contractors, Inc. (“MEB”) responded to Henrico County’s (“Henrico”) Request for Proposals (“RFP”) for the design and construction of a sport and convocation center (the “Project”). Henrico initially shortlisted Clark and MEB as a “design-build” team for the Project, but later restarted the search, issuing a second RFP. Clark and MEB submitted a second “design-build” proposal, but Henrico selected Rebkee Co. (“Rebkee”) for certain development aspects of the Project. MEB also submitted proposals to Rebkee, and Rebkee selected MEB as the design-builder for the Project. MEB, at Rebkee’s request, solicited proposals from three design firms and ultimately selected Clark as its design partner. From December 2019 to May 2020, Clark and MEB served as the design-build team to assist Rebkee in developing the Project. In connection therewith, Clark developed proprietary designs, technical drawings, and, with MEB, several cost estimates. In February 2020, MEB submitted a $294,334.50 Pay Application to Rebkee for engineering, design, and Project development work. Rebkee never paid MEB. Henrico paid MEB $50,000.00 as partial payment for MEB’s and Clark’s work. MEB then learned that Rebkee was using Clark’s drawings to solicit design and construction proposals from other companies. On July 23, 2020, Rebkee told MEB that Henrico directed it to cancel the design-build arrangement with MEB and Clark and pursue a different planning method. MEB and Clark sued and Rebkee for, among other claims, tortious interference with a business expectancy. Rebkee moved to dismiss the tortious interference claim. Continue reading Where Breach of Contract and Tortious Interference Collide

Construction Contract Basics: No Damages for Delay

After WAY too long a hiatus, I am back with another in my series of “Construction Contract Basics” posts.  In past posts, I’ve covered venue provisions, attorney fee provisions, and indemnity clauses.  In this post, I’ll share a few thoughts (or “musings”) on the topic of so-called “no damages for delay” clauses.  These clauses essentially state that a subcontractor’s only remedy for a delay caused by any factor beyond its control (including the fault of the general contractor), after proper notice to the owner or general contractor, is an extension of time to complete the work. Continue reading Construction Contract Basics: No Damages for Delay

Proper Notice Can “Accelerate” Your Recovery

Originally posted 2012-07-02 09:00:23.

Map of the United States District Courts in Vi...
Map of the United States District Courts in Virginia (Photo credit: Wikipedia)

I have discussed the importance of every word in a construction contract on multiple occasions at Construction Law Musings.  The United States District Court for the Western District of Virginia recently gave another reminder that one area that can act as a sword or shield in a contract is the language regarding provision of notice.

Continue reading Proper Notice Can “Accelerate” Your Recovery

Are Construction Contract Limitation of Liability Clauses on the Way Out in Virginia?

Remember BAE Systems and Fluor?  This post is the third here at Construction Law Musings relating to this case which is a seemingly never-ending source for content.  In the prior post discussing this case, the Court found that Va. Code 1-4.1:1 which bars waiver of a right to payment before work is performed did not apply because Fluor had provided work before execution of the contract or any change orders.

In the most recent opinion in this long-running litigation,  and after a motion to reconsider by Fluor that was granted, the Court re-examined this finding along with the contractual language found in the Limitation of Damages (LOD) clause and came to the opposite conclusion regarding certain change orders that remained unpaid by BAE. Continue reading Are Construction Contract Limitation of Liability Clauses on the Way Out in Virginia?

Uniwest Rides Again (or, Are Architects Subject to Va. Code Section 11-4.1?)

Originally posted 2018-10-03 11:07:55.

In 2010, the Virginia Supreme Court held in Uniwest Const., Inc. v. Amtech Elevator Servs., Inc., that Va. Code Sec. 11-4.1 renders completely void and unenforceable any indemnification provision in a construction contract between a contractor and subcontractor that seeks to indemnify the indemnified party from its own negligent acts.  In short, the Virginia Supreme Court stated that such overly broad provisions violate Section 11-4.1.

A recent case out of the Eastern District of Virginia Federal District Court examined a provision in a contract between a designer/architect and a contractor or owner on a project.  In Travelers Indem. Co. of Conn. v. Lessard Design Inc. the Court examined the application of Section 11-4.1 to the following provision of a design contract where Lessard, the indemnitor, agreed to:

[i]ndemnify, defend and hold the Owner, Owner’s Developer, and Owner’s and Owner’s Developer’s wholly owned affiliates and the agents, employees and officers of any of them harmless from and against any and all losses, liabilities, expenses, claims, fines and penalties, costs and expenses, including, but not limited to reasonable attorneys’ fees and court costs relating to the services performed by the Architect hereunder . . .

Continue reading Uniwest Rides Again (or, Are Architects Subject to Va. Code Section 11-4.1?)