Construction Contract Basics: No Damages for Delay

After WAY too long a hiatus, I am back with another in my series of “Construction Contract Basics” posts.  In past posts, I’ve covered venue provisions, attorney fee provisions, and indemnity clauses.  In this post, I’ll share a few thoughts (or “musings”) on the topic of so-called “no damages for delay” clauses.  These clauses essentially state that a subcontractor’s only remedy for a delay caused by any factor beyond its control (including the fault of the general contractor), after proper notice to the owner or general contractor, is an extension of time to complete the work. Continue reading Construction Contract Basics: No Damages for Delay

Proper Notice Can “Accelerate” Your Recovery

Originally posted 2012-07-02 09:00:23.

Map of the United States District Courts in Vi...
Map of the United States District Courts in Virginia (Photo credit: Wikipedia)

I have discussed the importance of every word in a construction contract on multiple occasions at Construction Law Musings.  The United States District Court for the Western District of Virginia recently gave another reminder that one area that can act as a sword or shield in a contract is the language regarding provision of notice.

Continue reading Proper Notice Can “Accelerate” Your Recovery

Are Construction Contract Limitation of Liability Clauses on the Way Out in Virginia?

Remember BAE Systems and Fluor?  This post is the third here at Construction Law Musings relating to this case which is a seemingly never-ending source for content.  In the prior post discussing this case, the Court found that Va. Code 1-4.1:1 which bars waiver of a right to payment before work is performed did not apply because Fluor had provided work before execution of the contract or any change orders.

In the most recent opinion in this long-running litigation,  and after a motion to reconsider by Fluor that was granted, the Court re-examined this finding along with the contractual language found in the Limitation of Damages (LOD) clause and came to the opposite conclusion regarding certain change orders that remained unpaid by BAE. Continue reading Are Construction Contract Limitation of Liability Clauses on the Way Out in Virginia?

Uniwest Rides Again (or, Are Architects Subject to Va. Code Section 11-4.1?)

Originally posted 2018-10-03 11:07:55.

In 2010, the Virginia Supreme Court held in Uniwest Const., Inc. v. Amtech Elevator Servs., Inc., that Va. Code Sec. 11-4.1 renders completely void and unenforceable any indemnification provision in a construction contract between a contractor and subcontractor that seeks to indemnify the indemnified party from its own negligent acts.  In short, the Virginia Supreme Court stated that such overly broad provisions violate Section 11-4.1.

A recent case out of the Eastern District of Virginia Federal District Court examined a provision in a contract between a designer/architect and a contractor or owner on a project.  In Travelers Indem. Co. of Conn. v. Lessard Design Inc. the Court examined the application of Section 11-4.1 to the following provision of a design contract where Lessard, the indemnitor, agreed to:

[i]ndemnify, defend and hold the Owner, Owner’s Developer, and Owner’s and Owner’s Developer’s wholly owned affiliates and the agents, employees and officers of any of them harmless from and against any and all losses, liabilities, expenses, claims, fines and penalties, costs and expenses, including, but not limited to reasonable attorneys’ fees and court costs relating to the services performed by the Architect hereunder . . .

Continue reading Uniwest Rides Again (or, Are Architects Subject to Va. Code Section 11-4.1?)

Fraud, the VCPA and Construction Contracts

Originally posted 2014-11-10 09:36:15.

Image via Wikipedia

I’ve discussed the economic loss rule here at Musings on several occasions.  The economic loss rule basically states that where one party assumes a duty based in contract or agreement, the Virginia courts will not allow a claim for breach of that duty to go forward as anything but a contract claim.  This doctrine makes fraud claims nearly, though not absolutely, impossible to maintain in a construction context.  In a majority of instances, fraud and construction contracts are very much like oil and water, leaving parties to fight it out over the terms of a particular contract despite actions by one party or the other that non-lawyers would clearly see as fraud.

However, a recent case decided by the Virginia Supreme Court gives at least some hope to those who are seemingly fooled into entering a contract that they would not other wise have entered into.  In Philip Abi-Najm, et. al, v Concord Condominium, LLC, several condominium purchasers sued Concord under for breach of contract, breach of the Virginia Consumer Protection Act (VCPA) and for fraud in the inducement based upon flooring that Concord installed that was far from the quality stated in the purchase contract.  Based upon these facts, the Court looked at two questions:  1.  Did a statement in the contract between Concord and the condo buyers create a situation in which the merger doctrine barred the breach of contract claim, and 2. Did the economic loss rule bar the VCPA and fraud claims?

After analyzing the merger claim and determining that the merger doctrine did not bar the breach of contract claim, the Court moved on to its analysis of the VCPA and fraud in the inducement claims.  In both instances, the Court determined that the causes of action would stand.  It reasoned that the VCPA created an independent statutory requirement making it unlawful to misrepresent that goods are of  a particular quality.  Because this duty arose independent of the contract, the claim was not barred by the economic loss rule.

Similarly, the fraud in the inducement claim was not barred because the plaintiffs alleged that Concord deliberately misrepresented the quality of the flooring knowing that it would likely cost Concord the sales if it disclosed the actual quality of the floors.  In short, the fraud, as alleged, was independent of the contract because it was conceived to bring buyers in despite Concord’s having no intention to follow through on the quality of the floors.

The lesson here is that pleading matters and that not all is lost for a consumer or home buyer that thinks that he or she is subject to fraud.  However, the devil is in the details and in the details put into the pleadings.  Without pleading some independent duty outside of the contract, any fraud or other non-contract claim will fail.  The advice of an experienced Virginia construction attorney will help you parse through the facts and properly package them for presentation to the Court.

As always, I welcome and encourage your comments below, please share your thoughts.  Also, please subscribe to keep up with the latest Construction Law Musings.