Reasonableness of Liquidated Damages Determined at Time of Contract (or, You Can’t Look Back Again)

Originally posted 2020-08-31 11:51:41.

construction photoI’ve discussed the continuing litigation between White Oak Power Constructors v. Mitsubishi Hitachi Power Systems Americas, Inc. previously here at Construction Law Musings because the case was another reminder that your construction contract terms matter and will be interpreted strictly here in the Commonwealth of Virginia.  The prior opinion in this case from the Eastern District of Virginia court the Court considered the applicability of a liquidated damages provision.  In the latest opinion from the Court (PDF) the Court looked at when and how any liquidated damages would be calculated.  In its June 22, 2020 opinion, the Court put the issue as follows:

White Oak’s motion for partial summary judgment presents a narrow issue: whether courts may consider the damages actually sustained by a party as a result of a contract breach when deciding if liquidated damages required by a contract “grossly exceed” a party’s actual damages.

Continue Reading

About Musings

About Construction Law Musings

I am a construction lawyer in Richmond, Virginia, a LEED AP, and have been nominated by my peers to Virginia's Legal Elite in Construction Law on multiple occasions. I provide advice and assistance with mechanic's liens, contract review and consulting, occupational safety issues (VOSH and OSHA), and risk management for construction professionals.

Please join the conversation!

Learn more about Construction Law Musings.