Thoughts on construction law from Christopher G. Hill, Virginia construction lawyer, LEED AP, mediator, and member of the Virginia Legal Elite in Construction Law

Tag Archives: Miller Act

Aarow Equipment v. Travelers- An Update

Originally posted 2015-01-12 09:00:08.

Seal of the United States Court of Appeals for...
Image via Wikipedia

Previously here at Musings, I discussed the application of pay if paid clauses and the Miller Act.  The case that prompted the discussion was the Aarow Equipment & Services, Inc. v. Travelers Casualty and Surety Co. case in which the Eastern District of Virginia Federal Court determined that a “pay if paid” clause coupled with a proper termination could defeat a Miller Act bond claim.  However, as I found out a couple of weeks ago at the VSB’s Construction Law and Public Contracts section meeting, the 4th Circuit Court of Appeals reversed and remanded this case in an unpublished opinion (Aarow Equipment & Services, Inc. v. Travelers Casualty and Surety Co.)

In it’s opinion, the 4th Circuit looked at some of the more “interesting” aspects of this case.  One of these circumstances was that Syska (the general contractor) directed Aarow to construct sedimentary ponds and other water management measures around the project (the “pond work”), which both agreed was outside of the scope of the work defined in their subcontract.  Syska asked that the government agree to a modification of the prime contract and asked Aarow to wait to submit its invoice for the pond work until after the government issued a modification to the prime contract and Syska issued a change order to the subcontract.

Several months later, no modification or change order had been issued, and Aarow submitted an invoice to Syska for the completed pond work. Syska instructed Aarow to list the pond work under a line item designated for certain finishing work on the project that had not yet been completed.  The government denied the subsequent change order request (submitted by Syska), stating that the pond work was in the scope of the original contract and Syska withheld money owed for other aspects of the work to make up the difference for the previously billed pond work.

Continue Reading

Reminder: Second Tier Subcontractors Have Miller Act Claim

Originally posted 2013-02-11 09:00:06. Here at Construction Law Musings, we often discuss the Federal Miller Act and its Virginia equivalent (the “Little Miller Act“).  These two statutes provide subcontractors on government projects (on which no mechanic’s lien can attach) the protection of payment and performance bonds. One question that often arises in this context is

Is Arbitration Okay Under the Miller Act? It Is if You Don’t Object

Originally posted 2014-10-13 09:15:01. I have discussed both payment bond claims under the Miller Act and alternate dispute resolution (ADR) here at Construction Law Musings on many an occasion.  A question that is sometimes open is what to do when there is contractually mandated arbitration for claims “relating to the contract or the work.” While

Contractor Side Deals Can Waive Rights

Originally posted 2014-04-09 16:16:54. Here at Construction Law Musings, we are quite fond of the Federal Miller Act and it’s Virginia counterpart, the “Little” Miller Act.  Both of these statutes allow a subcontractor or supplier on a government construction project the security to perform their work with the knowledge that a bonding company will back

About Musings

About Construction Law Musings

I am a construction lawyer in Richmond, Virginia, a LEED AP, and have been nominated by my peers to Virginia's Legal Elite in Construction Law on multiple occasions. I provide advice and assistance with mechanic's liens, contract review and consulting, occupational safety issues (VOSH and OSHA), and risk management for construction professionals.

Please join the conversation!

Learn more about Construction Law Musings.