Construction Contract Basics: No Damages for Delay

After WAY too long a hiatus, I am back with another in my series of “Construction Contract Basics” posts.  In past posts, I’ve covered venue provisions, attorney fee provisions, and indemnity clauses.  In this post, I’ll share a few thoughts (or “musings”) on the topic of so-called “no damages for delay” clauses.  These clauses essentially state that a subcontractor’s only remedy for a delay caused by any factor beyond its control (including the fault of the general contractor), after proper notice to the owner or general contractor, is an extension of time to complete the work. Continue reading Construction Contract Basics: No Damages for Delay

No Damages for Delay May Not Be Enforceable in Virginia

qimono @ PixabayAnyone who reads Construction Law Musings with any regularity (thank you by the way) knows that the contract is king in most instances here in Virginia.  Any commercial construction subcontractor in Virginia is likely also very familiar with so-called “no damages for delay” clauses in construction contracts.  These clauses essentially state that a subcontractor’s only remedy for a delay caused by any factor beyond its control (including the fault of the general contractor), after proper notice to the general contractor, is an extension of time to complete the work.  However, in 2015 the Virginia General Assembly passed a change in the law that precluded the diminishment of any right to claims for demonstrated additional costs prior to payment.  This left open the question as to which types of “diminishment” would be barred by the statute.

The recent case out of the Eastern District of Virginia federal court, Strata Solar LLC v. Fall Line Construction LLC, added a bit of clarity. Continue reading No Damages for Delay May Not Be Enforceable in Virginia

Exit mobile version