Happy Holidays from Construction Law Musings

Merry Christmas from Construction Law MusingsWe are nearing the end of another year and looking forward to the next.  For a shorter or longer time, all of the family is home for some Christmas cheer while Musings takes some holiday R&R.

I wish you all Happy Holidays and Merry Christmas from The Law Office of Christopher G. Hill, PC, and Construction Law Musings. To all of my friends, colleagues, and most importantly, family, I hope you have a safe, warm, and wonderful holiday.

Thank you for your continued support and I look forward to a great 2024 with you, my readers.

If you find this Musing to be interesting and have a comment, please join the conversation below and subscribe to keep up with the latest information.

Aarow Equipment v. Travelers- An Update

Originally posted 2015-01-12 09:00:08.

Image via Wikipedia

Previously here at Musings, I discussed the application of pay if paid clauses and the Miller Act.  The case that prompted the discussion was the Aarow Equipment & Services, Inc. v. Travelers Casualty and Surety Co. case in which the Eastern District of Virginia Federal Court determined that a “pay if paid” clause coupled with a proper termination could defeat a Miller Act bond claim.  However, as I found out a couple of weeks ago at the VSB’s Construction Law and Public Contracts section meeting, the 4th Circuit Court of Appeals reversed and remanded this case in an unpublished opinion (Aarow Equipment & Services, Inc. v. Travelers Casualty and Surety Co.)

In it’s opinion, the 4th Circuit looked at some of the more “interesting” aspects of this case.  One of these circumstances was that Syska (the general contractor) directed Aarow to construct sedimentary ponds and other water management measures around the project (the “pond work”), which both agreed was outside of the scope of the work defined in their subcontract.  Syska asked that the government agree to a modification of the prime contract and asked Aarow to wait to submit its invoice for the pond work until after the government issued a modification to the prime contract and Syska issued a change order to the subcontract.

Several months later, no modification or change order had been issued, and Aarow submitted an invoice to Syska for the completed pond work. Syska instructed Aarow to list the pond work under a line item designated for certain finishing work on the project that had not yet been completed.  The government denied the subsequent change order request (submitted by Syska), stating that the pond work was in the scope of the original contract and Syska withheld money owed for other aspects of the work to make up the difference for the previously billed pond work.

Continue reading Aarow Equipment v. Travelers- An Update

No Damages for Delay May Not Be Enforceable in Virginia

Anyone who reads Construction Law Musings with any regularity (thank you by the way) knows that the contract is king in most instances here in Virginia.  Any commercial construction subcontractor in Virginia is likely also very familiar with so-called “no damages for delay” clauses in construction contracts.  These clauses essentially state that a subcontractor’s only remedy for a delay caused by any factor beyond its control (including the fault of the general contractor), after proper notice to the general contractor, is an extension of time to complete the work.  However, in 2015 the Virginia General Assembly passed a change in the law that precluded the diminishment of any right to claims for demonstrated additional costs prior to payment.  This left open the question as to which types of “diminishment” would be barred by the statute.

The recent case out of the Eastern District of Virginia federal court, Strata Solar LLC v. Fall Line Construction LLC, added a bit of clarity. Continue reading No Damages for Delay May Not Be Enforceable in Virginia

The Construction Lawyer as Counselor

Originally posted 2019-04-24 10:56:09.

It’s been a while since I discussed the role that I believe a construction lawyer should serve.  Back in 2013, I discussed how those of us that practice construction law are seen as “necessary evils.”  I was thinking over the weekend about certain clients and matters (as I often do, particularly in the shower) and came to the conclusion that the best role for me as a Virginia construction attorney is that of counselor and sounding board for my clients.  Sure I come from a litigation background, enjoy working with other construction lawyers here in the Commonwealth, and often the first contact that I have with clients is when there is a problem, but I enjoy my practice, and I believe clients are more satisfied with their interactions with me when I try and provide a more cost effective and pragmatic solution than that which litigation or arbitration provides. Continue reading The Construction Lawyer as Counselor

Construction Law Musings Turns 15!

On this date back in 2008 (wow, that seems so long ago), I began Construction Law Musings on the Blogger platform with a brief announcement. Little did I know that this corner of the internet (or is it Blawgosphere?) would still be around in 2023!

In the time since I made that short entry 15 years ago (I know, I can’t believe it either), I’ve met several construction lawyers here in Virginia who refer to me as the “blog guy.”  To be recognized for the work I do here at Construction Law Musings, something that benefits me (and I hope the readers), and which I do for the fun of it, is an honor. Continue reading Construction Law Musings Turns 15!

Exit mobile version